Case Study: Providing Project Managed Services

Buscot Weir after the completion of Rotork’s extended scope contract, which encompassed project management, new valve actuation and adaptation, a new control panel in an adjacent building and the installation of a new walkway platform for inspection and maintenance.

Buscot Weir after the completion of Rotork’s extended scope contract, which encompassed project management, new valve actuation and adaptation, a new control panel in an adjacent building and the installation of a new walkway platform for inspection and maintenance.

Close-up of the obsolete sluice gate motor drives

Close-up of the obsolete sluice gate motor drives


Installation nearing completion on the new walkway platform; the IQ3 actuator in the foreground is fitted with its vandal-proof cover.

Installation nearing completion on the new walkway platform; the IQ3 actuator in the foreground is fitted with its vandal-proof cover.


A Rotork engineer confirms the successful operation of the new control panel during site commissioning.

A Rotork engineer confirms the successful operation of the new control panel during site commissioning.


Rotork is well known for supplying flow control equipment for new and upgraded industrial plants and processes on a global scale. In these contracts, often involving tens or hundreds of valve actuators and associated control equipment, Rotork works with valvemakers, engineering companies and end users as one of several members of a project team, each with different areas of expertise and generally all under the supervision of a main contractor.

Another part of Rotork’s activity involves actuators that are retrofitted on site as part of improvement projects which often also include additional work such as mechanical, electrical and civil engineering. The members of Rotork’s dedicated Site Services Division have many years experience of these projects, enabling them in many cases to organise the total supply of the work that is required together with project management services, embracing all of the project team disciplines in what is called an extended scope contract.

A major benefit for the customer is the simplified contractual route that the extended scope contract enables, by reducing the number of separate subcontractor contracts. Extended scope contracts have become particularly popular with customers in areas including water, power and environmental improvement, where projects can be relatively modest in scale but still demand a diverse range of engineering skills and disciplines. A recent Rotork UK contract for the Environment Agency at the picturesque village of Buscot in Wiltshire is a good example.

For many years Buscot Weir on the River Thames had been equipped with electric motors that were used to adjust the position of two sluice gates in order to manage the river level and flow rate during fluctuating weather conditions. These motors, with the associated valve shafts and an electrical control panel in an adjacent building, had become obsolete and required replacement to safeguard the river banks from potential flooding in the future.

As well as replacing all the obsolete equipment, the Environment Agency wished to ensure that future inspection and maintenance could be carried out safely. To achieve this it would be necessary to construct a new access walkway platform along the length of the weir. Following the preliminary site survey of the existing installation, Rotork Site Services submitted a contract proposal to the principle contractor AMCO Engineering which encompassed project management services and the total supply of all the elements of the project – new valve actuation, valve adaptation, wiring and control panel, new walkway platform, removal of old equipment, installation of new and commissioning.

Upon acceptance of the proposal, Rotork engineers returned to site to carry out a detailed survey to enable the replacement equipment to be dimensioned, designed and fabricated and to organise all the other equipment needed for the installation work such as scaffolding and temporary access. In this case it includedthe provision of pontoons by a company that specialises in safeguarding working environments when the presence of water is a potential hazard.

Rotork’s design team was able to replace the two existing electric motors with a single IQ3 electric valve actuator to operate both sluice gates simultaneously, driving through a combination of new shafting and three gearboxes supplied by Rotork Gears. The IQ3 actuator is certified as watertight and temporarily submersible to IP68, providing secure environmental protection for long term reliability in all anticipated ambient conditions. As the installation is adjacent to a public footpath, additional security is provided by the fitting of a vandal-proof cover over the actuator’s local control buttons to prevent any unauthorised operation or interference.

Rotork Site Services co-ordinated the manufacture and fabrication of all the new equipment and materials required for the upgrade. When this was completed, engineers from Rotork and the sub-contractors were back on site to remove the old equipment, install the new actuator and valve shafting with control panel, wiring, walkway platform and all associated ancillaries, completing the installation and commissioning within seven days.

Rotork UK
Tel: +44 1225 733200
www.rotork.com


Published: 5th March 2014

BVAA Strengthens Board with New Members

Rachel Wormald, Managing Director at YPS Valves Ltd and Elizabeth Waterman, ...

Share on Twitter Share on LinkedIn Read full article

BVAA Valve & Actuator Training News

Are you looking for industry-leading, brand independent valve and actuator ...

Share on Twitter Share on LinkedIn Read full article

Comment by BVAA CEO Rob Bartlett

As can be seen from the photograph, clearly the resident birds at Bartlett ...

Share on Twitter Share on LinkedIn Read full article

Howco Group Invests £1 Million in Vertical CNC Turning Centres

Howco Group has unveiled its latest £1million investment, with the ...

Share on Twitter Share on LinkedIn Read full article

Allvalves: Fuelling Growth Through Customer Connectivity

In 2024, Allvalves is poised for an exciting year of growth and expansion, ...

Share on Twitter Share on LinkedIn Read full article

GMM Pfaudler - Introducing the Normag Brand to the BVAA Community

GMM Pfaudler Engineered Plastics & Gaskets are delighted to bring the ...

Share on Twitter Share on LinkedIn Read full article

Building Industry Connections: A GMM Pfaudler Success Story

In the ever-evolving valve industry, GMM Pfaudler stands out for its ...

Share on Twitter Share on LinkedIn Read full article

SAMSON Controls Participates in the UK CCUS and Hydrogen Decarbonisation Summit

SAMSON Controls Ltd – part of the SAMSON group - a renowned leader in ...

Share on Twitter Share on LinkedIn Read full article