6 Step Inspection Safeguards Highest Quality for Oliver Valves

Published: 25th August 2022 | Issue 77 Share article:

At Oliver Valves we ensure that our valves are manufactured to the highest standard of quality. This involves putting specified valve components through a Liquid Penetrant Inspection (LPI) Process.

Stephen Andrews, workshop operative, has been co-ordinating our LPI process for the past 4 years. He explains “there are 6 steps to our inspection process, with each component carefully handled throughout. The process is detailed and thorough, designed to identify any indications or discontinuities of the components. This safeguards against any valves from reaching the final production stage that doesn’t meet with Industry Standard API 6A & ASME VIII.”

Our short-animated video walks you through the following LPI Process: LinkedIn Video 

  1. Pre-clean

          Components are pre-cleaned using a solvent cleaner and dried 

  1. Penetrant Solution Tank

          Components are coated with a fluorescent solution and then allowed to stand 

  1. Wash Off

          Excess fluorescent solution is removed from the surface 

  1. Drying Oven

          Components are dried at temperature 

  1. Developer Unit

          Components are coated with a developer for at least 10 minutes 

  1. Final Inspection & Post Clean

Components are inspected under UV light for indications and discontinuities. Components that don’t meet with Industry Standard API 6A & ASME VIII are removed.

Tel No:

+44 (0) 1565 632 636

Email:

sales@valves.co.uk

Website:

www.valves.co.uk 

LinkedIn:

https://www.linkedin.com/company/oliver-valves-ltd/ 

Search related articles:  

Recent magazine news articles